2500 kVA Step-up Transformers for Tanzania Mtwara Port
On March 20, 2026, TSTY Electric completed the equipment delivery for a power generation project at the Port of Mtwara, Tanzania. The shipment consisted of 20 units of 2500 kVA oil-immersed step-up transformers (voltage ratio: 0.415 kV / 11 kV). Housed within prefabricated enclosures, these units feature top-entry high- and low-voltage connections, a design without traditional oil conservator tanks, and a customized paint finish. They are intended to step up the low-voltage power generated by the generator sets to 11 kV for integration into the medium-voltage distribution system.

Project Overview
|
Project Elements |
content |
|
Project name |
Mtwara Port Power Project in Tanzania |
|
Project location |
Port of Mtwara, Tanzania |
|
Project Type |
Port-associated power generation |
|
Device Type |
Oil-immersed step-up transformer (integrated installation within a prefabricated enclosure) |
|
Number of devices |
20 units |
|
Capacity per unit |
2500 kVA |
|
Voltage ratio |
0.415 kV / 11 kV |
|
Key Customization |
Customized dimensions, top-mounted high- and low-voltage bushings, no traditional oil conservator, custom color, and off-circuit/on-load tap-changing configurations |
|
Delivery Time |
March 20, 2026 |
|
Manufacturer |
TSTY Electric Co.,Ltd(Founded in 1995, in Jia County, Pingdingshan, Henan Province) |
Five On-Site Constraints and Corresponding Resolutions
|
Site Constraints |
Transformer Requirements |
Project-Specific Solutions |
|
Limited interior space within the prefabricated enclosure |
External dimensions precisely match the internal layout |
The enclosure dimensions are customized based on the actual internal space and equipment spacing, with cable exit positions adjusted accordingly. |
|
The structure is non-standard; standard models cannot be used directly. |
Cable exit method, oil storage structure, and exterior design must be customized according to the project requirements. |
Top-entry connections for both high- and low-voltage sides; traditional oil conservator tank eliminated; paint finish customized according to the project’s color chart. |
|
Multiple devices need to be integrated; interfaces must be compatible. |
Coordinate spatially and electrically with the enclosure, busbar system, and grounding system. |
Confirm the cable exit orientation, phase-to-phase spacing, and connection method during the design phase. |
|
Supplier Onboarding for Overseas Projects |
System certification and testing documentation are complete and available for verification. |
Provides system certification, documentation of CNAS testing capabilities, and individual factory test reports for each unit. |
|
Batch of 20 units; high consistency requirements. |
Maintain consistency in dimensions, structure, color, and performance. |
Unified design parameters and process standards, inspection of critical production stages, and factory testing for every individual unit |
Core Equipment Configuration
|
Items |
Technical Configuration |
|
Product Name |
Oil-immersed step-up transformer |
|
Rated capacity |
2500 kVA |
|
Rated voltage on the low-voltage side |
0.415 kV |
|
Rated voltage on the high-voltage side |
11 kV |
|
Voltage conversion |
0.415 kV / 11 kV |
|
Number of devices |
20 units |
|
Installation Method |
Integrated installation within a prefabricated enclosure |
|
Qualification Path |
Top-entry connections for both high- and low-voltage sides |
|
Oil Conservator Configuration |
Without a traditional oil conservator |
|
Appearance requirements |
Specific dimensions, custom colors |
|
Pressure Regulation Configuration |
Off-load voltage regulation / On-load voltage regulation, to be confirmed in accordance with the project's technical agreement. |
|
Legal Basis for Enforcement |
Execute in accordance with the technical agreement in the contract; type test reports as per the IEC 60076 series can be provided. |

Key Points of the Electrical Scheme
1. Voltage step-up
The generator sets produce 0.415 kV low-voltage power, which is stepped up to 11 kV via a 2500 kVA transformer before being integrated into the medium-voltage distribution system. Increasing the voltage for a given power transmission level results in lower line current and reduced line losses.
2. Grouping configuration
The 20 generator units (of identical capacity) can be organized into groups based on power generation units or electrical circuits. The specific grid-connection method, operational grouping, and protection configuration shall be determined by the project’s primary system design.
3. Voltage regulation methods
Off-load (de-energized) tap changing requires a power outage to adjust the voltage setting; it suits slow-varying conditions such as seasonal voltage deviations. On-load (energized) tap changing allows adjustment while the system is under load, for scenarios with significant load fluctuations. The two methods differ in structure and operating requirements, so the choice must follow the system design; they are not interchangeable.
Manufacturing and Testing
The risk in batch customization does not lie in the inability to produce a single unit, but rather in the potential for inconsistency between the first unit and the twentieth. To address this, our control strategy for this project involves standardized design parameters, uniform process specifications, inspections of critical production stages for every individual unit, and mandatory factory acceptance testing (FAT) for each unit prior to release.
TSTY operates its own CNAS-accredited laboratory (Registration No. L25077; compliant with ISO/IEC 17025:2017; valid from January 19, 2026, to January 18, 2032; recognized under the ILAC-MRA). The laboratory’s testing capabilities cover ten categories, including lightning impulse, temperature rise, no-load and load losses, power-frequency and induced withstand voltage, DC resistance, turns ratio, insulation resistance, and partial discharge. A comprehensive test report is provided with every unit upon delivery.
Key manufacturing processes include automated core stacking (with a 95% automation rate), constant-tension winding, vacuum drying, and vacuum oil filling, all supported by a full-process QR-code traceability system. These represent the company’s standard manufacturing capabilities, and this project will be executed in strict accordance with the standards stipulated in the contractual technical agreement.

Qualifications and Certifications
|
Certifications / Qualifications |
illustrate |
|
CNAS Laboratory Accreditation |
ISO/IEC 17025:2017; 2026-01-19 to 2032-01-18; ILAC-MRA mutual recognition |
|
ISO 9001 Quality Management System |
One of the three management systems |
|
ISO 14001 Environmental Management System |
One of the three management systems |
|
ISO 45001 Occupational Health and Safety Management System |
Corresponds to GB/T 45001 |
|
UL / cUL |
Product Certification for the North American Market |
|
CE(UDEM / ECM) |
EU Market |
|
GOST |
Russia and the CIS |
|
EAC |
Low voltage complete equipment |
Frequently Asked Questions
Can a 2500 kVA transformer fit into a prefabricated enclosure?
Yes, provided that the external dimensions and cable/busbar outlet orientation are customized to suit the internal clearance of the enclosure. Standard transformer models often conflict with the outlet positioning or maintenance access paths; therefore, it is essential to verify the dimensions against the enclosure layout drawings during the planning phase.
How is the change in oil volume compensated for if there is no oil conservator (expansion tank)?
The design must specify the appropriate tank type and compensation mechanism, while also accounting for sealing, insulation, and thermal operating conditions. The specific solution is determined based on the project’s technical agreement; a standard transformer’s oil tank cannot simply be used as a direct replacement.
How can consistency be guaranteed across 20 units?
Consistency is ensured through standardized design parameters and manufacturing processes, individual inspections for critical production steps, and comprehensive factory acceptance testing (FAT) for every unit, complete with individual test reports. Acceptance documentation for batch projects should include specific clauses regarding uniformity in dimensions and external appearance.
What is the lead time for such customized units?
Standard models typically ship within 2–3 weeks; for customized units, the lead time is calculated based on the production schedule once the technical agreement is finalized. For this specific project, the timeline from design confirmation to delivery will be as stipulated in the contract.
Are Factory Acceptance Tests (FAT) and third-party inspections possible?
Yes, Factory Acceptance Tests (FAT) and on-site third-party inspections are both acceptable. All factory tests are conducted by a CNAS-accredited laboratory, which will provide the corresponding test reports.
Project Timeline
|
Stage |
Content |
|
Requirement Communication |
Confirm the internal layout, cable outlet requirements, color, and pressure regulation configuration. |
|
Technical Solution |
Develop and iterate through three versions of the customized solution, verifying parameters, dimensions, and interfaces at each stage. |
|
Standard edition |
Align with the project’s overall system design and confirm technical agreements. |
|
Production and Testing |
Organize batch production based on unified design parameters, with individual factory testing for each unit. |
|
deliver |
Delivery to be completed by March 20, 2026 |
About TSTY Electric
Founded in 1995 in Jia County, Pingdingshan, Henan Province, and renamed Pingdingshan TSTY Electric Co., Ltd. in 2011, TSTY Electric operates three intelligent manufacturing bases. The company has an annual production capacity of 25,000 transformers, 20,000 sets of high- and low-voltage complete equipment, and 6,000 package substations. With 158 patents filed to date, the company’s products and services reach over 3,500 enterprises across more than 100 countries, supported by over 10 overseas service centers and an agency network spanning 10 nations.
The product portfolio includes oil-immersed transformers (6–330 kV), dry-type transformers, American- and European-style package substations, prefabricated modular substations, high- and low-voltage switchgear, and integrated step-up units designed for wind power, photovoltaic, and energy storage applications.
