Comprehensive Power Solutions for Ghana EPC

November 27, 2026

TSTY Electric Co., Ltd. is a Chinese manufacturer with over 30 years of experience in power equipment production. we provide power transformers, prefabricated substations, medium and low voltage switchgear, and battery energy storage systems to EPC contractors, engineering general contractors, industrial project developers, and energy project investors in Ghana.

TSTY's production base is located in Jia County, Pingdingshan City, Henan Province, China, covering a total area of ​​approximately 500,000 square meters. It has a CNAS-accredited laboratory and holds 158 patents, including 67 invention patents.

The company's main products include:

- Oil-immersed and dry-type transformers, with a manufacturing capacity up to 100 MVA.

- Prefabricated and box-type substations, with a maximum capacity of 10,000 kVA.

- 12 kV, 24 kV, and 40.5 kV medium-voltage switchgear and low-voltage switchgear assemblies.

- Industrial and commercial energy storage, photovoltaic-energy storage systems, and large-scale containerized energy storage products.

TSTY provides equipment selection, technical documentation, product manufacturing, factory testing, export delivery, and project technical support for EPC projects in Ghana. The company has extensive experience in Ghanaian market and can provide corresponding power equipment configuration solutions based on the specific needs of each project.

TSTY Electric Co., Ltd.

Why did Ghana's EPC contractor choose TSTY Electric?

For EPC projects in Ghana, technical coordination among transformers, switchgear, package substations, and energy storage equipment is of critical importance.

TSTY’s strength lies not merely in supplying individual products, but in its comprehensive manufacturing capability—encompassing everything from transformers and complete switchgear assemblies to energy storage systems—which enables the company to provide a more complete equipment package for such projects.

Manufacturing and R&D Capabilities

Enterprise Data

Industry Experience

30+ years

Total land area of ​​the production base

500,000 m²

laboratory

CNAS accredited laboratories

Total number of patents

158 items

Invention Patent

67 items

Participate in national standards

19 items

Participate in industry standards

22 items

Participate in Group Standards

35 items

Countries to which products are exported

100+

 

Four power equipments for EPC procurement requirements

Main Power Transformer
Main Power Transformer
100 MVA
66 / 110 / 220 kV
SF6 Gas Insulated Switchgear (GIS)
SF6 Gas Insulated Switchgear
40.5 kV
GIS · 12 / 24 / 40.5 kV
Compact Transformer Substation
Compact Transformer Substation
10,000 kVA
IP54 / IP55
Liquid-cooled Energy Storage System
Liquid-cooled Energy Storage System
1000 kWh
C&I ESS · battery + PCS + BMS

 

 

Equipment scope for a 33/11 kV substation in Ghana

 

A 33/11 kV EPC substation combines a power transformer, MV switchgear, a 400 V distribution board and protection — plus the civil works the contractor controls. The table below shows what TSTY supplies for that scope and the standard each item is tested to, so the equipment list can be matched to a bill of quantities directly.

Equipment

Typical rating

Role in the substation

Standard

Power transformer

5–100 MVA, 33/11 kV

Steps 33 kV down to 11 kV

IEC 60076

Distribution transformer

30–2,500 kVA, 11/0.415 kV

Final step to low voltage

IEC 60076

Compact substation

up to 10,000 kVA

Transformer, RMU and LV board in one enclosure

IEC 62271-202

MV switchgear

11 kV / 33 kV, AIS or GIS

Switching, protection and metering

IEC 62271-200

LV switchboard

400 V

Distribution, motor control, changeover

IEC 61439

Battery storage

100 kWh – 5 MWh

Peak shaving, diesel reduction, solar firming

UL 9540A, IEC

All four product lines are manufactured in Jiaxian, Henan, on a 500,000 m² site transformer and switchgear workshops and a CNAS-accredited testing laboratory. Supplying them from one factory is what removes the interface risk between three separate vendors.

 

Power Transformers

Power transformers for 33/11 kV and 161 kV substations

The power transformers for 33/11 kV substations are a standard TSTY product, built from 5 MVA to 100 MVA with ONAN or ONAF cooling, off-circuit or on-load tap changers, and Dyn11 or YNd11 vector groups. Impedance is set per project so that downstream fault levels stay inside the switchgear rating, and loss values are guaranteed in the contract rather than quoted as typical.

Rating

Voltage ratio

Cooling

Short-circuit impedance

Vector group

Tapping

5 MVA

33/11 kV

ONAN

7.5% (per project)

Dyn11

OCTC ±2 × 2.5%

10 MVA

33/11 kV

ONAN / ONAF

8% (per project)

Dyn11 / YNd11

OLTC ±8 × 1.25%

20 MVA

33/11 kV

ONAF

9% (per project)

YNd11

OLTC ±8 × 1.25%

 

For 161 kV interconnection work, transformers are built to the same IEC 60076 regime with impulse-tested windings and site-assembled bushings; those units are quoted individually because transport and erection planning decide the design as much as the electrical specification does.

Distribution transformers at 11/0.415 kV

Distribution transformers from 30 kVA to 2,500 kVA are the highest-volume item on most Ghanaian EPC scopes: factory buildings, industrial parks, mines and utility reinforcement. TSTY builds them at 11/0.415 kV with Dyn11 connection, ONAN cooling and OCTC ±5% tapping, matching the 415/240 V low-voltage network used by ECG and by private industrial estates.

Loss performance, not price, is what determines lifecycle cost on these units. Measured values for two standard ratings are listed below; the 2,000 kVA figures are the guaranteed values from the TÜV Rheinland certificate of conformity.

Rating

Voltage

No-load loss

Load loss at 75 °C

Impedance

Notes

500 kVA

11/0.415 kV

680 W

5,410 W

4%

Routine-tested per unit

1,000 kVA

11/0.415 kV

1,150 W

10,300 W

4.5%

Routine-tested per unit

2,000 kVA

21/0.8 kV

≤ 1,305 W

≤ 15 kW

6% ±10%

Guaranteed values, TÜV CoC AK 50728320 0001

TSTY Electric Co., Ltd.

Dry-type transformers for indoor substations

Dry-type transformers run from 30 kVA to 31,500 kVA at 10/11 kV, 20/22 kV and 33/35 kV, and are specified where oil is unacceptable: basement substations, plant rooms, tunnels, and buildings where a fire load or an oil-containment sump is not permitted. Cast-resin construction removes the oil handling and oil testing that liquid-filled units require through their life.

Losses, impedance and tap ranges

Aspect

Oil-immersed

Dry-type

When to choose

Cooling

ONAN / ONAF

AN / AF

Oil where outdoor space and maintenance access exist

Fire behaviour

Oil-filled, needs bunding

Self-extinguishing cast resin

Dry-type for indoor, basement, densely occupied buildings

Typical impedance

4–6.5% distribution; 7.5–10% power

6%

Match to upstream protection settings

Tapping

OCTC ±5%, or OLTC ±8 × 1.25%

OCTC ±2 × 2.5%

OLTC where the supplied voltage swings daily

Condition monitoring

Oil BDV, moisture, DGA

Winding temperature, partial discharge

Oil units need an oil-testing routine on site

 

 

Compact and prefabricated substations

A compact substation puts the transformer, a ring main unit, the LV distribution board and the protection relays into one factory-assembled enclosure, tested as a unit before shipment. TSTY builds them up to 10,000 kVA with a 40.5 kV high-voltage side and a 12 kV or 0.69 kV low-voltage side, rated IP54 or IP55 and tested for −40 °C to +40 °C ambient.

The reason EPC contractors specify them is schedule and civil works, not floor area alone:

Aspect

Compact substation

Conventional substation building

Footprint

6–12 m² for 630–2,000 kVA 

40–80 m² including switch room and cable basement

Civil works

Concrete plinth and cable entry only

Building, cable trench, ventilation, fire separation

Site installation

1–3 days after delivery

6–10 weeks including building works

Relocation

Possible as a complete unit

Not practical

Rating range

up to 10,000 kVA

unrestricted

Factory testing

Transformer, RMU and LV board tested together

Each item tested separately by its own supplier

 

That last row is the one that changes project risk: one factory acceptance test covers the whole assembly, so interface faults between transformer and switchgear surface before shipment rather than during energisation.

TSTY Electric Co., Ltd.

 

MV and LV switchgear

11 kV and 33 kV switchgear

TSTY supplies metal-clad and gas-insulated switchgear for 12 kV, 24 kV and 40.5 kV systems: KYN28A-12 and KYN28A-24 for indoor metal-clad boards, KYN61-40.5 where 33 kV is required, HXGN-12 ring main units for compact substations, and GIS where space or pollution demands a sealed design.

Model

Voltage

Type

Typical application

Standard

KYN28A-12

12 kV

Metal-clad, withdrawable

11 kV incomers and feeders

IEC 62271-200

KYN28A-24

24 kV

Metal-clad, withdrawable

20/22 kV systems

IEC 62271-200

KYN61-40.5

40.5 kV

Metal-clad, withdrawable

33 kV substations

IEC 62271-200

HXGN-12

12 kV

Ring main unit

Compact substations, distribution rings

IEC 62271-200

GIS

12–40.5 kV

Gas-insulated

Confined space, high pollution

IEC 62271-200

BlokSeT

400 V

LV switchboard

Main distribution, motor control

IEC 61439

 

 

Rated current and short-circuit ratings are selected per project: [C7]. Because the switchgear and the transformer come from the same factory, the through-fault rating of the board and the impedance of the transformer are checked against each other before the drawings are released, instead of after delivery.

LV main switchboards at 400 V

Low-voltage boards are built on Schneider BlokSeT technology, with ACB or MCCB incomers, motor control centres, automatic transfer switching and capacitor banks for power-factor correction. They are assembled and routine-tested in the same workshop as the MV panels, which keeps the earthing and interlocking design consistent between the two voltage levels.

Protection and metering interface

Protection is coordinated across the transformer, the MV feeder and the LV main breaker: overcurrent and earth-fault settings on the MV side are chosen against the transformer damage curve, and the LV breaker is set below the transformer through-fault capability. Where the EPC provides its own protection study, TSTY issues the relay setting files and the CT/VT ratios needed to complete it.

 


 

Battery energy storage for EPC projects

Containerised lithium storage from 100 kW / 101 kWh to 1,000 kW / 5,015 kWh covers the three cases EPC contractors bring to Ghanaian sites: shaving diesel consumption at mines, firming a solar plant, and cutting demand charges at industrial facilities. Systems ship with PCS, EMS and fire-suppression design integrated.

 


 

33/11kV Transformer & Substation Application

Package

Contents

Typical project

Voltage

Distribution substation package

Transformer, RMU, LV board, protection

Factory, industrial park, commercial development

33/11 kV, 11/0.415 kV

Industrial plant package

Power transformer, MV switchgear, LV distribution

Mine, cement plant, processing facility

33 kV or 11 kV

Solar-plus-storage package

Step-up transformer, MV switchgear, battery storage

IPP, mine hybrid plant, captive solar

11/33 kV

 


 TSTY’s Comprehensive Equipment Solutions for EPC Projects in Ghana

Option 1: Industrial power distribution system

TSTY Electric Co., Ltd.

Recommended equipment combination
  • Oil-immersed or dry-type transformers
  • Medium voltage KYN28A / GIS / Ring main unit
Industrial EPC, manufacturing plants, industrial parks, mining contractors.
Option 2: Photovoltaic power plant and step-up power distribution

TSTY Electric Co., Ltd.

Recommended equipment combination
  • Photovoltaic Step-Up Transformer
  • Prefabricated Substation
  • Medium Voltage Switchgear
  • Supporting Low Voltage Electrical Equipment
Target Customers: Photovoltaic EPC, Solar Project Developers, Energy Engineering Companies
Option 3: Photovoltaic + Energy Storage System

TSTY Electric Co., Ltd.

Recommended equipment combination
  • C&I Energy Storage System
  • Battery System and Supporting Control Equipment
  • PCS / EMS System (determined based on product and project scope)
  • Step-up Transformer
  • Medium and Low Voltage Switchgear
Target Customers: Photovoltaic-Storage EPC, Energy Storage Project Developers, Industrial Energy Project Investors
Option 4: Power supply for mines and mining industries

TSTY Electric Co., Ltd.

Recommended equipment combination
  • Industrial Power Transformers
  • Medium Voltage Switchgear
  • Low Voltage Distribution and Control Cabinets
  • Prefabricated Substations
Target Customers: Mining EPC, Mining Operators, Mineral Processing Plants

 

 

TSTY’s Project Experience in the Ghanaian Market

TSTY possesses relevant experience with mining projects in Ghana, covering various mining applications and electrical equipment designed for the mining sector.

Mining projects demand high levels of power supply reliability, equipment adaptability, and robustness for on-site operating conditions. TSTY provides tailored transformer and power distribution equipment configurations based on project technical specifications and actual load requirements.


TSTY can supply the following, as required by your project:                          
- Product technical data sheets.                          
- Transformer loss data.                          
- Type test reports for the relevant products.                          
- Product compliance documentation.                          
- Equipment outline drawings and technical specifications.                          
- Documentation for project tenders and technical submittals.                          
 

Furthermore, TSTY can provide distribution transformer loss test data and energy efficiency label designs to assist clients with local registration and compliance filings in Ghana. For project tenders and technical evaluations, TSTY can prepare comprehensive technical submittal packages based on the specific product data.

 


 

TSTY’s Manufacturing, Delivery, and After-Sales Support

TSTY has a production base in Henan, China, primarily manufacturing transformers, box-type substations, high- and low-voltage switchgear, and energy storage equipment; it also operates a laboratory accredited by CNAS.

Items

TSTY Current Conditions

Factory location

Jia County, Pingdingshan City, Henan Province

Conventional transformer lead time

15–25 days

Default port of shipment

Qingdao Port can be adjusted according to customer requirements.

Payment methods

T/T, L/C or other Negotiable payment methods

Payment Terms

100% prepayment, 30% prepayment + 70% before shipment, or other negotiated payment terms.

Standard warranty

1 year

Optional warranty

2-5 years

Spare parts supply

Shipped from Chinese factory, approximately 2–4 weeks.

 


 

Installation, testing and handover

Installation is executed by the EPC; TSTY provides supervision, oil processing and the pre-commissioning programme. The checks below are the ones that most often stop energisation when they are skipped.

Test

What it confirms

Insulation resistance

Winding and bushing integrity after transport

Turns ratio and vector group

Nameplate conformity and parallel-operation suitability

Winding resistance

Connection quality and contact resistance

Short-circuit impedance

Match to the protection study

Oil breakdown voltage and moisture

Oil condition before energisation

Protection relay settings

Coordination with the upstream feeder

Interlock and safety shutter checks

Operator safety under fault conditions

Earthing continuity

Substation earthing integrity

 

 

Handover documentation includes as-built drawings, routine test records, O&M manuals, a spare-parts list and the commissioning report. Commissioning engineers are dispatched from China, and spare parts ship from the factory, typically within 2–4 weeks.

 


 

Schedule risks and how we control them

Three failure modes account for most equipment-related delay on Ghanaian EPC projects. Each has a control that is written into the purchase order rather than promised in a meeting.

Risk

What it costs the EPC

How TSTY controls it

Delivery slips against a construction milestone

Liquidated damages, idle labour, re-sequenced works

Production slot locked at purchase order; weekly progress report with photographs

Specification deviation found at drawing approval

Re-design, 4–6 week delay, re-quote

Clause-by-clause compliance review before the order is placed, not after

Customs delay at Tema

Storage charges, missed energisation date

Pre-shipment document review with the clearing agent; advance ruling where classification is unclear

 

FAQ for EPC Clients in Ghana

 

Can you supply transformer, switchgear and battery storage under one contract? +
Yes. Transformers, compact substations, MV and LV switchgear and storage are manufactured in the same Jiaxian plant, so one order covers the package, one factory acceptance test covers the assembly and one warranty contact covers every item.
Do you attend factory acceptance tests?  +
Testing is witnessed at the Jiaxian plant. The FAT procedure is issued before the test date, and the EPC or a nominated third-party inspector may attend; records and oscillograms ship with the equipment.
Who handles customs clearance?  +
TSTY quotes EXW, FOB, CIF or other Transportation methods. Commercial invoice, packing list, certificate of origin and test reports are issued before shipment.
What warranty do you give on transformers? +
Twelve months from commissioning is standard, with 24 months available on request. Cover is for manufacturing defects, and loss guarantees are backed by the routine test certificates issued with each unit.
Do you provide installation supervision in Ghana?  +
We will sense the customer's needs and arrange for our technicians to go to the site to help with on-site debugging, installation, etc.
Do you supply spare parts?  +
A recommended spare-parts list is issued with the offer, covering bushings, gaskets, tap-changer contacts, relays and fuses. Stocked items ship from the factory in 2–4 weeks; there is no parts warehouse in Ghana.
What are your payment terms? +
 T/T or letter of credit. Standard terms are 30% with the order and 70% before shipment, or 100% in advance; other structures can be agreed where the contract requires performance security.
Can you supply 33/11 kV transformers as standard? +
Yes.  33/11 kV transformers are a standard product, with ONAN or ONAF cooling and OLTC tapping. Larger units are engineered per project against the utility specification..

 